Prior Gram Sabha Consent Mandatory: SC Sets Aside Sundargarh Mining Land Acquisition
Sunderghar- The Supreme Court of India has set aside the Odisha government’s land acquisition for a Dalmia Cement Bharat Limited mining project in Sundargarh district. Ruling that prior consent from local village assemblies (Gram Sabhas) is strictly mandatory in Scheduled Areas, the top court invalidated the entire acquisition process.A two-judge bench comprising Justice Dipankar Datta and Justice Satish Chandra Sharma overturned a September 2024 Orissa High Court verdict that had previously allowed the acquisition to proceed.
Mandatory Gram Sabha Consent: Interpreting Section 41(3) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013, the bench held that prior consent from the Gram Sabha is an absolute requirement before acquiring land in Fifth Schedule tribal areas. It cannot be bypassed or treated as optional
80% Family Consent Required: Because the land was being acquired specifically to hand over surface rights to a private company, the court ruled that Section 2(2)(b) of the 2013 Act required the prior consent of at least 80% of affected families alongside the Social Impact Assessment—not gathered piecemeal at later stages.
Adivasi Villagers Vindicated: The petition was led by Bibol Toppo and residents of Kukuda, Bihabandha, and Lanjiberna villages. While Dalmia Cement held a limestone and dolomite mining lease over 893.55 hectares (extended until 2040), the state had moved to acquire roughly 273.57 hectares/acres of surface agricultural land across these three villages despite the Gram Sabhas unanimously rejecting the proposal.
High Court Reversed: The Supreme Court rejected the Orissa High Court’s earlier reasoning that consent rules did not apply because the state was initially acquiring the title before transferring it. It also flagged procedural flaws, including a conflict of interest in the Social Impact Assessment expert group.
While declaring the current acquisition notifications “unsustainable” and setting them aside, the Supreme Court granted the Odisha government the liberty to initiate fresh acquisition proceedings—strictly provided it follows all statutory safeguards and obtains the required Gram Sabha and family consents under the 2013 law.